A 50-metre section of a newly constructed road in Gosairhat, Shariatpur, has collapsed just seven days after the carpeting work was completed. The road was built at a cost of Tk 6.78 crore. In addition to the major collapse, smaller sections of the same road have caved in at five other locations, while large cracks have appeared at four more points. Local residents fear that the cracked sections could collapse at any moment.
Local residents allege that soil taken from a nearby canal was used during road construction without proper piling or other necessary protective measures. They also claim that the same 50-metre section that has now collapsed had previously caved in once during the construction period. However, the contractor and the Upazila Local Government Engineering Department (LGED) attribute the damage to prolonged rainfall, which they say softened the soil and caused the road to collapse and develop cracks at several points.
According to local residents and LGED sources, the road construction project was undertaken under the Important Upazila and Union Road Widening and Strengthening Project in the Dhaka Division. The project involved constructing approximately 4,120 metres of road from Lakachua to Samantasar Bazar in Samantasar Union of Gosairhat Upazila. The estimated construction cost was Tk 6.78 crore.
Following a tender process, the contract was awarded to a construction firm named Pragati Enterprise. The work was carried out by Ziaur Rahman Zia Jamaddar, convener of Gosairhat Municipality BNP.
The road carpeting work was recently completed. However, just seven days later, a section spanning approximately 50 metres collapsed. Asphalt and the underlying soil have washed away from the affected area, leaving behind a large hole. Smaller sections have also collapsed at at least five other locations, while significant cracks have appeared across four sections of the road.
Residents fear that without immediate intervention, the cracked portions could also collapse. This could disrupt traffic on the road and potentially lead to serious accidents.
Local residents said they had raised concerns about soil filling and the road’s durability during construction. They particularly alleged that soil excavated from the adjacent canal was used in the road. However, they claimed that no necessary piling or protective measures were taken along the canal bank and other vulnerable sections. As a result, they believe that soil erosion has caused cracks and collapses at several points.
Residents also stressed that the road is an important transportation route for people in Samantasar Union, with various vehicles using it every day. The damage and cracks have now made travelling along the road a matter of concern. They have called for immediate repairs to the collapsed sections, proper protective measures at the cracked locations, and an investigation into the quality of the construction work.
Local resident Ruhul Amin said, “This section was already collapsing while the road was being constructed. At that time, they used an excavator to collect soil directly from the nearby canal and dump it here. We warned them that using this soil would cause the road to collapse again, but they did not listen. They simply laid some sand and stone chips before applying the asphalt. Now it has collapsed again. If they had repaired it properly after the first collapse, this would not have happened today.”

When contacted, contractor Ziaur Rahman Jamaddar said the prolonged rainfall had caused the soil beneath the road to shift, resulting in the collapse.
“As the project is still under construction, we will resolve the issue,” he said.
Responding to allegations made by local residents, he added, “What local people say is not important. What do they know about construction work?”
Meanwhile, Upazila LGED Engineer Abul Kalam Azad declined to make an on-camera statement when contacted about the incident.
However, in an unofficial conversation recorded without his knowledge, he reportedly said, “I cannot give any statement. It will create problems for me. You do not need to take any statement from us. Just talk to Brother Zia, and that will be enough.”